At Cachet, building visionary communities that families will be proud to call home is a mission that we take seriously. We are excited to share the recent progress we’ve made at Bradford Urban Towns, Cachet ParQ, Generations in the Village of Ayr, Mount Hope by Cachet and Westwood Village. We are one step closer to welcoming you home.

Bradford Urban Towns

Foundation walls are complete on Blocks 1 to 7, with Blocks 8 and 9 being poured.  Underground mechanicals are being installed as our team prepares to form the last suspended slab on Blocks 3 and 4.  Our servicing contractor will be mobilizing to complete the road work and underground infrastructure prior to commencement of framing.

Cachet ParQ

Foundation walls are now complete on Blocks 6, 7, 9, 10, 11 and 13, with forming crews working on completing Blocks 5, 8 and 12. Our framing contractor is well underway on Blocks 11 and 9. Installation of hydro and gas utility service to the subdivision will begin shortly as this project continues to take shape.

Generations in the Village of Ayr

Construction activity is now in full swing with over 30 basement foundations poured. Our forming crews continue to push forward on the remaining units. Carpentry has begun on multiple units and homes begin to rise.

Mount Hope by Cachet

All Phase 1 units are now occupied, and final plans are being made to begin landscaping and sodding. Phase 2 detached homes and townhomes are beginning to close, with full occupancy anticipated by mid summer. Top curb and sidewalk will begin shortly with landscape and sodding to follow.

Construction activity on Phase 3 and 4 is in full force as multiple carpenters, bricklayers and interior trades make progress on these homes. Concrete forming of all homes in these phases is expected to be completed by mid June.

Westwood Village

Our utility contractor has nearly completed installation of hydro and gas services for the homes in Phase 1 and will move directly onto Phase 2. Road asphalt in Phase 2 is scheduled to begin mid June. Residential construction has begun on Phase 1 detached homes, with basement foundations complete on 10 units and carpenters starting to frame lots. 